Blue Origin Launch Complex

Customer: Turner Construction

Description: What began as a $3.5 million design-assist contract for the flame deflector component of the launch facility evolved into a broader partnership with Blue Origin and Turner Construction Company on the development of Launch Complex 36.

Over the course of the project, more than 655 tons of structural steel were fabricated and installed across the facility. Met-Con’s scope included steel framing for the launch pad, the flame deflector insert, multiple surrounding work platforms, and the custom transport apparatus used to move rockets within the launch complex.

The project required innovative problem-solving, close collaboration with the project team, and precise execution to meet the demanding requirements of a next-generation aerospace launch facility.

A low-angle documentation photograph of a massive industrial aerospace site, showcasing a tall rocket vertical on its launchpad tower, surrounded by complex structural steel networks under a bright, clear sky.
A wide, low-angle documentation photograph of a large-scale industrial aerospace construction site, featuring an intricate network of freshly erected gray structural steel columns, framing, and heavy cross-bracing beams under a bright, clear sky.
A dramatic night photograph of a large-scale industrial aerospace site, showcasing a massive rocket vertical on a launchpad, illuminated by bright spotlights under a dark night sky.
A wide, low-angle documentation photograph of a massive industrial aerospace site, showcasing a tall commercial rocket standing vertical on its structural steel launchpad tower under a bright, clear blue sky.

View More of Our Work

Structural steel framework for the Artemis II launch complex at Kennedy Space Center, fabricated and installed by Met-Con, Inc.

Artemis II

Customer : Comet Description: Support of critical launch infrastructure for the Artemis II mission at Kennedy Space Center , including work associated with the ML1 Mobile Launcher and facilities supporting NASA’s next-generation deep space exploration program. As the...

read more...
A wide daytime photograph showcasing the modern exterior architecture of the completed UCF College of Nursing building facility, featuring clean design lines and manicured green lawns under a clear sky, with structural steel framing installed by Met-Con, Inc.

UCF College of Nursing

Customer : DPR Description: Fabrication and erection of structural steel for the Dr. Phillips Nursing Pavilion , a $68 million, 90,000-square-foot academic health sciences facility on the University of Central Florida Lake Nona Campus delivered by DPR Construction ....

read more...